Client
Enterprise Gold Mine
Works
Mesh drape, rope access, telehandler
Completion Date
01/2017

RAM were awarded the contract to install 8,000m2 of Geobrugg Deltax at the Enterprise Gold Mine on short notice. All plant, equipment and materials were mobilise to site within 24hrs. The installation was completed by RAM IRATA Rope Access crew with the use of a telehandler with rated lifting points to add to the ease of installation. Due to the rapid mobilisation by RAM and the smooth installation of the rock fall system, Norton Goldfields were able to avoid major delays.