Project - K2RQ (Kingsrove to Reevsby Quadruplication)

K2RQ - RAIL CORRIDOR SHORING WITH SOIL NAILS & SHOTCRETE

Project:                                     Kingsgrove to Revesby Rail Quadruplication
Client:                                       RailCorp
Principle Contractor:                K2RQ Alliance
Total metres drilling:                 7,500               
Total number of soil nails:        In excess of 1,500        
Design Types:                          Soil nails with double corrosion protection      
Anticipated completion:            March 2010

 

Drilling of holes for soil nails.   Drilling of soil nails prior to installation.
The RIX Group are demonstrating our expertise and capabilities at K2RQ, embracing the challenges of working within the rail corridor to deliver superior work to RTA Quality Assurance Specifications R64 and R68 in areas typically with limited access and at heights up to 12m.
 
Soil nail integration in to the reinforcement steel prior to shotcreting   The soil nail wall, now shotcreted with a consistent architectural finish
 
By utilising our highly trained and professional in-house site teams and purpose designed drills rigs, grout stations and shotcrete rigs, The RIX Group are delivering 10,000m2 of shotcrete walls including 7500m of permanent soil nails to the K2RQ project.